The Eiland Boulevard Pavemant Rehabilitation Project is schduled to begin the week of May 13, 2019. The paving project incudes both the eastbound and westbound lanes of Eiland Boulevard - from Handcart Road to Fort King Road
The road will include milling and resurfacing, as well as new pavement markings and restriping.
Work hours: Sunday through Thursday, 7:00pm - 7:00am
Epect single lane closures with message boards directing traffic.
Target completion date is June 19, 2019, depending on weather conditions.
Monday May 13, 2019 Wednesday Jun 19, 2019
Start the week of May13, 2019 Sunday through Thursday 7:00pm - 7:00am
Eiland Boulevard from Handcart Road to Fort King Road
Printed courtesy of www.eastpascochamber.org/ – Contact the Greater East Pasco Chamber of Commerce for more information.
38550 5th Avenue, Zephyrhills and Dade City, FL 33542 – (813) 782-1913 – ceo@eastpascochamber.org